Voltage withstand tests must be conducted between each energized phase and the grounded enclosure. For enclosures housing all three phases, each phase shall be tested individually, with the enclosure and the other two phases grounded. Prior to commencing voltage withstand tests, all power transformers, surge arresters, protective gaps, power cables, overhead transmission lines, and voltage transformers must be disconnected. Voltage transformers can be tested up to the saturation voltage of the transformer at the test frequency.
Voltage withstand tests are to be carried out between each energized phase and the grounded enclosure. In enclosures with all three phases, each phase should be tested one at a time, while the enclosure and the other two phases are grounded. The insulation between each pair of phase conductors does not require any additional field voltage withstand tests.
Before starting voltage withstand tests, all power transformers, surge arresters, protective gaps, power cables, and overhead transmission lines must be disconnected. Voltage transformers should be tested up to their saturation voltage at the test frequency.
Isolating sections of the GIS apparatus can offer an added advantage of field - testing the open gap of some disconnecting switches, though such a field test is not obligatory. Additionally, it may be necessary to isolate sections of the GIS to facilitate the location of a disruptive discharge or to limit the energy potentially released during a disruptive discharge.
A partial discharge measurement can be performed to detect any possible intrusion of conductive particles or damage to high - voltage insulating components that might have occurred during factory testing, transportation, or installation. The gas - insulated switchgear should be essentially free of partial discharge. The procedure for partial discharge measurement and its interpretation should be provided by the manufacturer and agreed upon between the user and the manufacturer.
DC voltage withstand testing is not advisable for a completed GIS. However, it might be necessary to conduct a DC voltage withstand test on power cables connected to a GIS. These test voltages would inevitably be applied from the end of the cable opposite to the GIS, thus subjecting a small part of the GIS to the DC voltage. It is recommended to keep the portion of the GIS exposed to this DC voltage as small as possible. The manufacturer should be consulted before conducting these tests.
Dielectric, continuity, and resistivity tests should be carried out on all interconnecting control wiring installed in the field.
After the GIS has been assembled at the job site, the following aspects need to be verified:
- The torque value of all bolts and connections assembled in the field must be checked to ensure compliance with the specified requirements.
- The control wiring should be verified to conform to the schematic and wiring diagrams.
- The proper functioning of each electrical, pneumatic, hydraulic, mechanical, key - operated, or combined interlock system needs to be verified for correct operation in both permissive and blocking conditions.
- The proper operation of controls, gas, pneumatic, and hydraulic monitoring and alarming systems, protective and regulating equipment, operation counters, including heaters and lights, must be confirmed.
- Each mechanical and electrical position indicator for each circuit breaker, disconnect switch, and grounding switch should be verified to accurately indicate the device's open and closed positions.
- The gas zones, gas zone identification, gas valves, gas valve positions, and interconnecting piping should be verified to be in line with the physical drawings.
- The operating parameters such as contact alignment, contact travel, velocity, opening time, and closing time of each circuit breaker, disconnect switch, and grounding switch must be verified according to the specified requirements.
- The correct operation of compressors, pumps, auxiliary contacts, and anti - pump schemes should be verified to meet the specified requirements.
- The circuit breakers need to be trip - tested at minimum and maximum control voltages to confirm correct operation.
- The secondary wiring should be verified to have correct wire lugs, proper crimping, tightened terminal block screws, correct wire and cable markers, and wiring in accordance with the manufacturer's drawings.
Once the gas - insulated substation has been fully installed, wired, and all field tests have been successfully completed, the new apparatus is ready to be connected to the existing electrical system. This process involves another set of tests to verify protective relay operation, the ability of circuit breakers to trip upon remote command, and proper phase relationships with various transmission lines. This second series of tests is expected to be similar, if not identical, to the tests carried out on an air - insulated substation (AIS).